MSA Project Update

 

A Review of MSA Projects in Your Community

Date: November 7, 2007

 

Client Liaison:Mike Laue

920-887-4242

mikel@msa-ps.com

 

On-site Engineer: Bob Uelmen

920-210-0126

ruelmen@msa-ps.com

A flurry of activity along E. Center St., including concrete

pavement installation on October 18 th near city hall.

E. Center Street Project:

All of the sanitary/water/storm facilities have been completed. Crews from Ptaschinski Construction have completed the concrete pavement installation from N. Main St. to N. Mill St. and are currently excavating for road base, installing granular base material, concrete curb/gutter and driveway approaches. Crews from Henshue Construction (Madison), working for Dodge County, have completed the installation of underground conduits on the western half of the project for fiber optic cables. The underlying poor soil conditions on the westerly three quarters of the project have been addressed by extending the excavation below normal road subgrade and filling with large stone to provide a stable base for constructing the road surface. The updated schedule calls for the following approximate dates:

  • Curb/gutter, driveway aprons, sidewalk repair thru mid-November
  • Asphalt pavement and landscaping thru mid-November
  • Street lighting by the Juneau Electric Utility thru the end of November

 

Outdated curb stop valves were uncovered on a majority of the

of the existing services and have been replaced. In the past,

these valves were allowed to have a bleeder hole to release air,

however this design was determined to be defective in that it

could also allow contaminants to enter the water system.

 

 

 

 

 

 

 

The former well building and EMS/Fire Department garage at 100 Lincoln Drive has been renovated and is now the headquarters for the Juneau Electric Department.

Phone 920-386-4808
Fax 920-386-4803

E-Mail agentz@cityofjuneau.net
Hours 6:30 AM to 4:00 PM Monday - Thursday and Friday 6:30 AM to 10:30 AM (May 15th to September 15th)
7:00 AM to 3:30 Monday - Friday (September 15th to May 15th)
Location 100 Lincoln Drive
 
Playground equipment was upgraded during the summer of 2003 at the city park located on Lincoln Drive.
 
 

The city took occupancy of the recently constructed Public Safety Building at 128 E. Cross Street in of June, 2004. The Police Department, EMS, and Fire Department operate out of the new building.

 
 
 
Eight campsites at the new Wild Goose Park will be available in mid-July. Coin-operated showers can be accessed near the campsites.
 
The Warming Shelter located in Wild Goose Park provides restrooms, showers, pay phone & soda machines. For rental information contact the City Hall.
Back to the City of Juneau homepage